按照《施工合同文本》规定,在施工中由于下列哪些因素造成工期延误,经发包人代表确认,竣工日期可以顺延?
A.承包人未能及时调配施工机械
B.发生不可抗力
C.雨季天数增多
D.工程量变化和设计变更
E.一周内非承包人原因停电、停水、停气等造成停工累计超过8小时
正确答案是BDE