试在题37所编绘的箭线式网络图中,确定关键线路并用双线(或粗黑线)表示出来,计算总工期和A、B、C三项活动最早完成时间(要求写出计算过程)。
关键线路B,D,E,F;总工期19天;EF(下标A)=0+2=2EF(下标B)=0+5= 5EF(下标C)=2+5=7