某项目实施后净现值及概率分别为:1200万元,概率0.4;400万元,概率0.3;-800万元,概率0.3.该项目的期望净现值为
A.800万元
B.600万元
C.480万元
D.360万元
正确答案是D
扫描二维码免费使用微信小程序搜题/刷题/查看解析。
版权声明:本文由翰林刷题小程序授权发布,如需转载请注明出处。
本文链接:https://doc.20230611.cn/post/172383.html
上一篇:根据中国仲裁法和司法解释的有关规定,下列哪些事项是不能提交仲裁的? ( )
下一篇:Robert Spring, a 19th century forger, was so good at his profession that he was able to make his living for 15 years by selling false signatures of famous Americans. Spring was born in England in 1813 and arrived in Philadelphia in 1858 to open a boo