()列出了项目所需的、待排序的全部进度活动,这些活动的依赖关系和其他制约因素会对活动排序产生影响,是活动识别的成果 。
A.
进度管理计划
B.
活动清单
C.
活动属性
D.
里程碑清单
正确答案是B