说明该项目的关键线路
网络计划中,自始至终全部由关键工作组成的线路或线路上总的工作持续时间(总工期)最长的线路叫作关键线路。该项目的关键线路有AEFG和ACDE,但具关键线路的定义来看,该项目的关键线路是:AEFG。